25 21st Century Schools Programme - New Gowerton Primary School. PDF 73 KB
Minutes:
The Cabinet member for
Learning and Skills presented a report which sought to:
·
To approve the
scheme for the new build for Gowerton Primary School
subject to confirmation of grant and contract with Welsh Government.
·
To seek
authorisation to award the 2nd Stage Contract for the works to
Tender No. 1, subject to confirmation of grant and contract with Welsh
Government.
·
To approve the
appropriation of the proposed site at The Elba.
CABINET DECISION |
|
That: 1.
The capital
scheme as detailed together with the financial implications set out in
Appendix A is approved, subject to confirmation of grant and contract with
Welsh Government and; 2.
The contract
for the works to build a new school for Gowerton
Primary be awarded to Tender No. 1 subject to confirmation of grant and
contract with Welsh Government and; 3.
As no
objections to the appropriation have been received, the Appropriation of the
land from the Director of Place to the Director of People is approved which
will enable the building of the proposed new Gowerton
Primary School; 4.
The Head of
Legal, Democratic Services and Procurement is authorised to enter into any
necessary documentation required to complete the contract and achieve the
scheme. |
|
Policy
Framework |
|
· The Review and Capital Budget as reported to and
approved by Council on the 18th February 2014. · Corporate Priority to review the overall provision
of schools. · Corporate Priority to improve opportunities for
children and young people. · Corporate Priority improving school performance. · Corporate Priority effective corporate and strategic
management of assets. |
|
Reason
for Decision |
|
· To comply with Financial Procedure Rule 7 (Capital
programming and Appraisals) – to commit and authorise schemes as per the
Capital Programme. · To comply with Contract Procedure Rule 13, the
evaluation and award of contract. ·
Statutory
requirement under S.122 (2A) of the Local Government Act 1972 to consider any
objections to the proposed appropriation of an open space. |
|
Consultation
|
|
Education, Finance, Legal Services, Corporate
Building and Property Services. |