103 Capital Budget & Programme 2024/25 - 2029/30. PDF 171 KB
Additional documents:
Decision:
Approved.
Minutes:
The Presiding Member set out the process that would be
followed for this item.
The Section 151 Officer submitted a report that proposed a revised capital budget for 2024/25 and a capital budget for 2025/26 – 2028/29.
Original report proposed by Councillor R C Stewart. Seconded
by Councillor A S Lewis.
The Presiding Member stated that two budget amendments had been received from the Uplands Group and from the Labour Group.
Uplands Group Amendment
Proposed by Councillor S J Rice. Seconded by Councillor P N
May.
The amendment being:
· Remove: Skyline £8.072m.
Following debate and a vote, the amendment was not
supported.
Labour Group Amendment
Proposed by Councillor R C Stewart. Seconded by Councillor A
S Lewis.
The amendment being:
Add £1m for 2026/27 taking total investment to £2m for modern changing rooms.
Following debate and a vote, the amendment was supported.
The amendment became the substantive motion.
Substantive Motion
Discussion took place on the substantive motion.
Resolved that the revised capital budget for 2024/25 and
the capital budget for 2025/26 – 2029/30, as amended and detailed in appendices
A, B, C, D, E, F and G, be approved.
104 Capital Budget & Programme 2024/25 - 2029/30. PDF 170 KB
Additional documents:
Minutes:
Call In Procedure – Subject to Pre-Decision Scrutiny: This decision is exempt from the Authority’s Call In Procedure as “the decision has been subject to Pre-Decision Scrutiny and there is no material change in relevant information / evidence”.
The Section 151 Officer submitted a report that proposed a revised capital budget for 2024/25 and a capital budget for 2025/26-2029/30.
Resolved that:
1)
The revised
capital budget for 2024/25 and the capital budget for 2025/26-2029/30 as
detailed in Appendices A, B, C, D, E, F and G of the report be approved.
2)
The
additional funding as detailed in Paragraph 2.6.2 of the report be allocated as
follows:
i)
£1,000,000, one off payment into the Community Investment
Fund.
ii)
£395,000 annual payment into Parks Equipment Machinery.
3)
A technical adjustment be made for the
extra capital spend associated with the expected final Local Government
Borrowing Initiative (LGBI) scheme announcement.