Additional Funding Requirements for the Remodelling and Refurbishment Project at Bishopston Comprehensive School.

A Contract Award report and Financial Procedure Rule 7 (FPR7) report was presented to and approved by Cabinet on the 7 May 2020, recommending that the contract be awarded to Kier Western Ltd.

 

A Full Business Case (FBC) was approved by Welsh Government in July 2020.

 

Due to various challenges, including COVID-19, insufficient provisional sums and unforeseen build issues, we are now seeking to commit further funding from the Band B programme.

Decision type: Key

Decision status: Recommendations Approved

Notice of proposed decision first published: 10/06/2022

Decision due: 21 Jul 2022 by Cabinet

Lead member: Cabinet Member - Education & Learning

Lead director: Director of Education

Contact: John O'Brien, School Project Planning Implementation Officer.