Castle Square Regeneration FPR7.

A phased regeneration scheme is being prepared for Castle Square from feasibility, through to design, planning and implementation. This report summarises the current short list of design options, outcomes from consultations, RIBA stage 2/3 scheme costs and seeks funding from the capital budget and authorisation to deliver the project during 2022/23.

Decision type: Allweddol

Decision status: Recommendations Approved

Notice of proposed decision first published: 10/09/2021

Decision due: 16 Dec 2021 by Cabinet

Lead member: Cabinet Member - Investment, Regeneration, Events & Tourism

Lead director: Director of Place

Contact: Gail Evans, Principal Regeneration Manager Email: gail.evans@swansea.gov.uk.