This project is part of Band B
of the 21st Century Schools Programme and if approved will be jointly funded by
Welsh Government and Swansea Council. The project provides for the extension
and remodelling of the current Y G Gwyr school site enabling an increase in
capacity of the school so that it can accommodate 1273 pupils and meet the
current and projected demand. The project is subject to full business case
approval by Welsh Government. This report is seeking approval to award the
contract in accordance with Contract Procedure Rule 13.10 and commit the scheme
to the capital programme in accordance with Financial Procedure 7.
The report submitted to Corporate Briefing will be subject to finalisation
prior to a Special Cabinet on the 23 January once the tender process has been
conducted in accordance with the Public Contracts Regulations 2015 and the Council’s
Contract Procedure Rules. A Special Cabinet is required to enable Cabinet to
approve the award of contract and commitment to the capital programme, at the
earliest opportunity and to avoid any avoidable delay in the delivery of the
project.
Decision type: Key
Decision status: Recommendations Approved
Notice of proposed decision first published: 11/10/2019
Decision due: 23 Jan 2020 by Cabinet
Lead member: Cabinet Member - Education & Learning
Lead director: Director of Education