Following a statutory
consultation process in March 2019 Cabinet approved that the capacity of YGG
Tan-y-lan increases to 420 plus nursery in a new build school at Beacons View
Road, Clase.
Welsh Government approved in principle the Outline Business Case in December
2018. Planning approval was obtained on the 7 May 2019. A construction tender
process was conducted during June and July 2019. The Responsible Officer is
satisfied that the tender process has been conducted in accordance with the
Public Contracts Regulations 2015 and the Council’s Contract Procedure Rules
and the award is recommended for approval on that basis.
This report is seeking approval to award the contract in accordance with
Contract Procedure Rule 13.10,
and commit the scheme to the capital programme in accordance with Financial
Procedure 7.
Decision type: Key
Decision status: Recommendations Approved
Notice of proposed decision first published: 20/09/2019
Decision due: 17 Oct 2019 by Cabinet
Lead member: Cabinet Member - Education & Learning
Lead director: Head of Service - Education, Planning & Resources
Contact: Louise Herbert-Evans, Head of Capital Planning and Delivery Unit Email: louise.herbert-evans@swansea.gov.uk.