Election of a Chair For The Remainder of the Municipal Year 2014-2015. Minutes: RESOLVED that Councillor P Lloyd be
elected Chair of the Committee for the remainder of the Municipal Year
2014-2015. Councillor P Lloyd (Chair) Presided |
|
Election of a Vice Chair For The Remainder of the Municipal Year 2014-2015. Minutes: RESOLVED that Councillor J C Bayliss be elected Vice Chair of the Committee for the remainder of the Municipal Year 2014-2015. |
|
Apologies for Absence. Minutes: Apologies for absence were
received from Councillors FM Gordon, JA Hale, B Hopkins, PM Matthews, J Newbury
and C Thomas. |
|
Disclosures of Personal and Prejudicial Interests. PDF 30 KB Minutes: In accordance with the Code
of Conduct adopted by the City and County of Swansea, no interests were
declared. |
|
To approve as a correct record the Minutes of the Meeting of the Area 1 Development Control Committee held on 16 September 2014. Minutes: RESOLVED
that the Minutes of the meeting of
the Area 2 Development Control Committee held on 16 September 2014 be
approved as a correct record. |
|
Items for deferral / withdrawal. Minutes: None. |
|
Determination of Planning Applications under the Town and Country Planning Act 1990. PDF 49 KB Additional documents:
Minutes: The Head of Economic
Regeneration and Planning submitted a Planning Application. Amendments to this schedule
were reported and are indicated below by (#). RESOLVED that: (1) the undermentioned planning application BE
APPROVED subject to the conditions in the report and/or indicated below #(Item 1) Application No.2014/0739 - Installation of a solar PV array,
construction of a storage room, invertor cabin, a substation, switchgear
building and fencing at Land to South of Gelliwern Isaf, Felindre, Swansea. Mrs H Morrall (agent)
addressed the Committee. A visual presentation was
given to Committee. Report updated as follows: Page
14, paragraph 5, lines 1 & 2 :
delete ‘(which will last approximately one month)’ Application approved subject
to the following amended conditions 2, 3, 4, 6, 7, 8,10,11 and 13. 2. No later than 12 months from the first
generation of electricity, the following schemes shall be submitted in writing
for the written approval of the Local Planning Authority: (i) A scheme detailing the removal of all surface
elements of the photo voltaic solar farm and any foundations or anchor systems
to a depth of 300mm below ground level; (ii) A scheme detailing the restoration and
aftercare, following consultation with such other parties as the Local Planning
Authority considers appropriate. These schemes shall be implemented in accordance with such details as
may be approved by the Local Planning Authority within 12 months from the date
of the last electricity generated should the site no longer be utilised for the
development hereby permitted. Reason: In the interest of visual amenity and to ensure the land is restored
in an acceptable manner. 3. No development approved by this permission
shall take place until a method statement detailing the provisions of suitable
facilities on site to ensure vehicles leaving the site do not deposit mud or
debris on the adjacent highway has been submitted to and approved in writing by
the Local Planning Authority. The method statement shall be implemented in
accordance with the approve details. Reason: In the interests of highway safety. 4. No development approved by this permission
shall take place until details of the methodology for the scope and nature of the
dilapidation surveys to be undertaken on the adopted highway have been
submitted to and approved in writing by the Local Planning Authority. The
dilapidation surveys shall be undertaken in accordance with the approved
details. Reason : In the interest of highway safety 6. No development approved by
this permission shall take place until details of a scheme for the
implementation, maintenance and management of a sustainable drainage system
(SUDS) for surface water drainage has been submitted to and approved in writing
by the Local Planning Authority. The approved scheme shall be implemented prior
to the construction of any impermeable surfaces draining to this system, unless
otherwise agreed in writing by the Local Planning Authority. The details shall include
calculations of the proposed swale to ensure that it is of adequate size. Reason: To prevent the increased risk of flooding by ensuring the provision of
a satisfactory means of surface water disposal. 7. No development approved by this permission
shall be commenced until a Site Waste Management Plan has been and submitted in
writing for approval by the Local Planning Authority. The plan shall be
implemented in accordance with the approved details. Reason: To ensure waste at the site
is managed in line with the Waste Hierarchy in a priority order of prevention,
re-use, recycling before considering other recovery or disposal option. 8. No development approved by this permission
shall take place until details of a scheme showing how the area in Compartment
8 that supports whorled caraway will be protected during construction and
demarcated by fencing or similar has been submitted to and approved in writing
by the Local Planning Authority. The scheme shall be implemented in accordance
with the approved details and shall be retained at all times unless otherwise
agreed in writing by the Local Planning Authority. Reason: In the interests of biodiversity 10 No development approved by this
permission shall take place until a scheme containing details of bird and bat
boxes to be placed around the site have been submitted to and approved in
writing by the Local Planning Authority. The scheme as approved shall be
implemented in accordance with the approved details and shall be retained at
all times unless otherwise agreed in writing by the Local Planning Authority. Reason: In the interests of biodiversity 11. Notwithstanding the details
submitted, details of a scheme for the design and siting of the access tracks,
including enlarged turn areas, shall be submitted to and approved in writing by
the Local Planning Authority prior to the commencement of development. The
scheme shall be implemented in accordance with the approved details. Reason: To protect the integrity of the pipeline easement in the interest of
public safety. 13. No development approved by this permission shall take place until
the applicant, or their agents or successors in title, has secured the
implementation of a programme of archaeological work in accordance with a
written scheme of investigation in the form of an archaeological watching brief
which has been submitted by the applicant and approved in writing by the Local
Planning Authority. Reason:
To identify and record any features of archaeological interest discovered during the works, in order to
mitigate the impact of the works on the archaeological resource. |